Information on the progress of the preparation of the state irrigation scheme for the vegetation period of 2018 as of April 27, 2018

To prepare the scheme for the vegetation period of 2018, as of April 27, 2018, across the Republic the works were performed for 185.2 million KGS with a plan of 190.0 million KGS or 98%. The following types of works were made using these funds:

  • repair of the canals with length of 400.1 km with planned 412.8 km or 97%;
  • mechanized cleaning of canals with length of 353.5 km, with planned 369.9 km or 96%;
  • repair of hydraulic structures - 1135 units with planned 1161 units or 98%;
  • repair of hydroposts - 1076 units with planned 1101 units or 98%;
  • repair of pumping stations - 96 units with planned 102 units or 94%;
  • repair of boreholes - 37 units with planned 39 units or 95%;

According to the work schedule, the preparation of the irrigation scheme for the vegetation season will be completed in:

       - Issyk-Kul and Naryn oblasts on May 1, 2018;

       - Orto-Tokoi, Kirov and Papan reservoirs, Batken, Osh, Jalal-Abad, Chui, Talas oblasts according to the schedule for the preparation for the vegetation in 2018 are ready to supply irrigation water.